Data groups cannot be ended - assure_mimix - 10.0

Assure MIMIX Operations Guide

Product type
Software
Portfolio
Integrate
Product family
Assure
Product
Assure MIMIX™ Software
Version
10.0
ft:locale
en-US
Product name
Assure MIMIX
ft:title
Assure MIMIX Operations Guide
Copyright
2026
First publish date
1999
ft:lastEdition
2026-01-13
ft:lastPublication
2026-01-13T10:54:54.977000
L1_Product_Gateway
Integrate
L2_Product_Segment
IBM Infrastructure
L3_Product_Brand
Precisely Assure
L4_Investment_Segment
IBM i HA
L5_Product_Group
IBM i HA
L6_Product_Name
Assure MIMIX

A controlled end for a data group may take some time if there is a backlog of files to process or if there are a number of errors that MIMIX is attempting to resolve before ending.

If you think that a data group is taking too long to end, check the following for possible causes:

  • Check to see how many transactions are backlogged for the apply process. Use option 8 (Display status) on the Work with Data Groups display to access the detailed status. A number in the Unprocessed Entry Count column indicates a backlog. Use F7 and F8 to see additional information.

  • Determine which replication process is not ending. Use the command WRKSBSJOB SBS(MIMIXSBS) to see the jobs in the MIMIXSBS subsystem. Look for jobs for replication processes that have not changed to a status of END. For example, abc_OBJRTV, where abc is a 3-character prefix.

  • Check the QSYSOPR message log to see if there is message that requires a reply.

  • You can use the WRKDGACTE STATUS(*ACTIVE) command to ensure all data group activity entries are completed. If a controlled end was issued, all activity entries must be processed before the object processes are ended.