To use a library project, you copy it into a Quality process workflow or an empty Quality project from either the Library or the Quality project, depending on the context in which you are working.
Note: When you copy a library project into a Quality project, the library project inherits
the target project's data processing
setting.
Copy from the Library
To copy from the Library
- In the Navigation or Icon View, right-click a library project and select Use. The Copy to Quality Project window opens.
- Select the target project into which you want to copy the library project. The list of processes for the selected project displays.
- Click OK to copy to the Quality project. (If you are copying into a project of another type, the Different Project Types window opens. Click Yes to continue or No to stop the process.) The scheduler bar opens.
- (Optional) Change the job name.
-
Do one of the following:
- To schedule the job to run immediately, click Now. The message closes and the job begins running in the background.
- Click Later. The Set Date & Time scheduler window opens. To immediately run the job in the background, click Run Now. To schedule a time, select a starting date on the calendar and select a time you want the job to run on the selected date. Click Submit to save the scheduled time.
- Click Cancel to cancel the task.
When the job finishes, note the following:
- The copied entity and process names display in the Navigation View under the target project.
- In the Quality Process Flow, the library processes are added to the right of the current project as a disconnected workflow. (You may need to scroll down or to the right to see the library project.).
- Real entities display as yellow icons with a red line; dynamic and imported entities display as white icons with a grey line.
- Complete the Add New Input procedure.
Copy from a Quality Project View
To copy from a Quality Project View
- Open the Quality project with which you want to work.
- Right-click outside the workflow and select Copy from project library. The Copy from library window opens.
- Select the library project you want to copy. The list of processes for the selected project displays.
- Click OK to copy the project from the library. The scheduler bar opens.
- (Optional) Change the job name.
-
Do one of the following:
- To schedule the job to run immediately, click Now. The message closes and the job begins running in the background.
- Click Later. The Set Date & Time scheduler window opens. To immediately run the job in the background, click Run Now. To schedule a time, select a starting date on the calendar and select a time you want the job to run on the selected date. Click Submit to save the scheduled time.
- Click Cancel to cancel the task.
When the job finishes, note the following:
- The copied entity and process names display in the Navigation View under the target project.
- In the Quality Process Flow, the library processes are added to the right of the current project as a disconnected workflow. (You may need to scroll down or to the right to see the library project.).
- Real entities display as yellow icons with a red line; dynamic and imported entities display as white icons with a grey line.
- Complete the Add New Input procedure.