You can copy entities created during profiling activities and paste them in your Quality projects.
To copy an entity from profiling
- Click the Entities tab on the Discover bar.
- Right-click the entity you want to copy and select Copy Entity to Quality Project.
- Click the Develop bar and double-click the Quality project you want to paste the entity to. The project is displayed in the Project View.
- Right-click anywhere in the project and select Paste Entity. The entity is displayed in the Project View. If you want to replace the input entity for a process, follow the next procedure.
To replace an entity for a process
- Right-click the process for which you want to replace the input entity and select Add new Inputs. If you want to replace the input entity for the project, right-click the first process in the project.
- Select the new entity.
- Click OK. The new entity is added to the process.
- Open the process for editing and select the Schema Editor tab.
- In the Schema Editor, select the Regenerate Output Schema check box. The Regenerate Output Schema section becomes available.
- In the Regenerate Output Schema section, select the new entity from the Using Input schema drop-down list.
- Select Inherit schema and click Apply.
- When the confirmation box opens, click OK. The output schema changes to match the new entity.
- Click Finish.
- Right-click the process and select Apply Schema Changes.
- When the confirmation box opens, click OK.
- After the schema change is completed, right-click the arrow from the old entity and select Remove this input, and then click OK. The process flow now only links to the new entity.
- Right-click the unattached old entity and select Remove Entity from
project. Note: You can remove an entity from a project only when the entity has been removed from all processes.