You can duplicate a process within a project or copy a process from one project to another.
Note: When you finish specifying the settings, click Finish to save any changes made
to the configuration for the process.
To copy a process
-
From the Navigation View, right-click the process and select Copy Process.
-
In Project View, open the project to which you want to copy the process.
-
Right-click and select Paste. The process is copied as a new process with new input and output entities. The new input and output entities are empty.
Note: You can also select and drag the process from the Navigation View to the
Project View.
-
Manually replace the input entity with another suitable existing input.