If you did not find a potential dependency you had expected you can create a new dependency.

Note: Dependencies do not support dynamic entities. Use only real entities to create dependencies.

To create a dependency

  1. Do one of the following:
    • On the Home tab, select Keys/Deps > Create.
    • In the Navigation View, right-click a real entity and select Create Key or Dependency.
    • In the Navigation View, from the Analysis tab, right-click Dependencies and select Create Dependency or right-click a Baseline Analysis project and select Analyze > Create Key or Dependency.

    The Create Key or Dependency window opens.

  2. Select Dependencies.
  3. Select the entity name from the drop-down list.
  4. Click Next.
  5. Enter a Job Name.
  6. Place a check next to each left-hand-side (LHS) attribute to use to create the dependency.
  7. Place a check next to one right-hand-side (RHS) attribute to use to create the dependency.
  8. Click Finish.
  9. Run the analysis now or schedule a time for the job to run later.