Configuring Iterator Activities - EnterWorks_Process_Exchange_(EPX) - 11.0

EnterWorks Process Exchange (EPX)

Product type
Software
Portfolio
Verify
Product family
EnterWorks
Product
Precisely EnterWorks
Precisely EnterWorks > EnterWorks Process Exchange (EPX)
Precisely EnterWorks > EnterWorks
Version
11.0
Language
English
Product name
Precisely EnterWorks
Title
EnterWorks Process Exchange (EPX)
Copyright
2024
First publish date
2007
Last updated
2024-02-29
Published on
2024-02-29T08:35:54.993000

To configure this activity:

  1. Place an Iterator Activity in the flow, right-click its icon, and click Properties in the shortcut menu.
  2. On the General tab, type a name for the activity in the Name box and a description (optional) in the Description box.
  3. Click the Details tab. If needed, select a new priority for work items.

    Note: This activity cannot be a starting point.

  4. Click the Settings tab.
  5. In the Counter box, type the name of the counter to be incremented. If the counter does not exist, it will be created with a value of 1.
  6. Click OK.