Completed Work Item Reports list the work items for a specified flow, that have completed the flow. To run a Completed Work Item Report:
Click Completed Work Item on the Navigator pane, and then select the process flow type and the specific flow from the content pane. Click Next.
Click a work item in the list of work items that appears, and then click Generate Report. The results of the Completed Work Item Report are displayed.
The name of the process flow appears at the top left corner of the content pane, the date and time the report was run appear in the top right corner. The information includes the work item creation and completion timestamps, the work item priority, and the work item properties. You can print the results of the report by clicking the Print button on your browser toolbar.
Note: You can sort the report data on any of the column headers but Properties.