The Work with Application Groups display provides a high level summary of status. During a switch, check for the following:

  • The values displayed in the App Status and Data Rsc Grp Status columns reflect the switch activity.

  • The Proc Status column should have a value of *ACTIVE while the switch is running for an application group. If *ATTN appears, the procedure may have stopped or require user action before it can complete. Use option 21 (Procedure status) to check the status of the procedure.

Figure 1. Example status of a switch in progress