This procedure switches operations to the backup system.
Before using this procedure, consult your runbook for any additional procedures that must be performed when switching to the backup system.
If this is a planned switch, Precisely strongly recommends that you perform a full set of audits with the most extensive checking available in auditing options. Use Performing audits before a planned switch.
Shut down all active applications that are reading or updating replicated objects from the production and backup systems.
Do the following from the backup system:
-
Ensure that all transactions have been applied to the backup system by doing the following:
-
Select option 6 (Work with data groups) from the MIMIX Basic Main Menu and press Enter.
- For each data group, select option 8 (Display status) and ensure that the Unprocessed entry counts for both database and object apply have no values.
-
- From the MIMIX Basic Main Menu, select option 5 (Start or complete switch using Switch Asst.).
- You will see the Confirm Switch to Backup confirmation display. Press F16 to confirm your choice to switch MIMIX and specify switching options.
- The Run Switch Framework (RUNSWTFWK) command appears. The default Switch
framework and the value *BCKUP for the Switch framework process are
preselected and cannot be changed. Do the following:
-
You must specify the type of switch to perform, *PLANNED or *UNPLANNED, at the Switch type prompt.
-
You can change values for other parameters as needed.
-
To start the switch, press Enter.
-
-
Consult your runbook to determine if any additional steps are needed.
After you complete this phase of the switch you must wait until the original production system is available again. Then perform the steps in Synchronizing data and starting MIMIX on the original production system.