Resolving a procedure status problem reported for an application group - assure_mimix - 10.0

Assure MIMIX Operations Guide

Product type
Software
Portfolio
Integrate
Product family
Assure
Product
Assure MIMIX™ Software
Version
10.0
Language
English
Product name
Assure MIMIX
Title
Assure MIMIX Operations Guide
Copyright
2023
First publish date
1999
Last updated
2024-03-12
Published on
2024-03-12T11:06:36.794496

The AG Proc Status column represents a summary of the most recent run of all procedures defined for the application group.

Important! Check the status of the AG Proc Status column and address any problem indicated by *ATTN or *ACTIVE status before attempting to resolve any problem reported in other columns on the Work with Application Groups display. Status shown in other columns will likely change after active procedures complete or procedures which require attention have been addressed.

Table 1. Summary of Procedure Status values that require attention

Column Value

Description and Action

*ACTIVE

One or more of the last started runs of the procedures to run are still active or queued. Wait for the procedure to complete. Do not attempt to correct other status problems reported on the display until the procedure completes. Use option 21 (Procedure status) to view the status of the last started runs of procedures.

*ATTN

One or more of the last started runs of the procedures have a status that requires attention. Resolve the procedure problems before attempting to correct other status problems reported on the Work with Application Groups display.

  1. Use option 21 (Procedure status) to view the status of the last started runs of the procedures.

  2. The resulting procedures shown on the Work with Procedure Status display which have status values of *ATTN, *CANCELED, *FAILED, *MSGW, or *PENDCNL require user action.

  3. It may be necessary to check status of the steps within the procedure to resolve a step problem before the procedure can continue. Use option 8 (Step status) to display step status for the procedure.

Note: For a virtual switch procedure (type *SWTVRT), a *MSGW status for step MXVRTRCY is expected and should remain unanswered for the duration of the testing phase of the virtual switch. Do not respond to the message for step MXVRTRCY until testing is complete and you are ready for the recovery phase of the virtual switch procedure. Return to the Work with Application Groups display to check for other reported problems with the application group that need to be resolved.

For detailed information, see Working with procedures and steps.

Note: The status *COMP is a summary status that indicates the most recently started run of each procedure for the application group has completed, completed with errors, or has an acknowledged status. For any individual procedure that completed with errors, user action is recommended to investigate the cause of the error and assess its implications.